Arngask Primary and Nursery School sits in the village of Glenfarg. Its main building dates from 1871, while the Early Years Building, completed in 2002, accommodates the nursery and P1/2 class.
Between October 2025 and November 2026, JGM worked in partnership with Perth & Kinross Council to renew the school’s mechanical and electrical services. Acting as both Principal Contractor and M&E Contractor, we delivered the technical installations and managed the wider programme.
The project brought together several disciplines. Mechanical and electrical installations had to align with civil engineering, scaffolding, joinery, fire-stopping, insulation, flooring and external works.
JGM planned the sequence and managed the points where these packages met. This kept the different trades connected and allowed the work to progress as one project rather than a series of separate tasks.
Regular communication with Perth & Kinross Council and the specialist contractors supported delivery from planning through to completion.
The mechanical scope included a full upgrade of the heating pipework and cold-water system. Two air-source heat pumps were installed, together with fan convector heaters throughout the school. The boiler house and Building Management System were also renewed.
The electrical infrastructure received an equally extensive overhaul. JGM installed a new MCCB panel, section panel board and distribution boards, as well as new submains cabling. Surge protection was added throughout the upgraded electrical system, and a new lightning protection system was fitted.
The wider scope included full upgrades to the boys’ and girls’ toilets and the installation of new security fencing.
Each stage depended on close cooperation between trades. LearnD delivered the BMS package, while BEST PTSG installed the lightning protection system. Parker Contracts completed the joinery and fire-stopping, supported by civil works from Calforth Construction and fixed scaffolding from Access Solutions.
McNicol insulated the new pipework, while H&V Commissioning Services carried out commissioning works for the building services. Melvin Brothers installed the security fencing, Veitchi completed the vinyl flooring and GT Diamond Drilling carried out the coring required for the new services.
JGM oversaw these individual packages, managed the interfaces between them and kept each team working to the same programme.
The completed works renewed the essential systems that keep the school warm, powered and running each day. Heating and water installations were replaced, controls modernised and the electrical infrastructure extensively upgraded. Improvements to the toilets and perimeter fencing completed the wider programme.
For JGM, the project demonstrates the value of combining M&E expertise with principal contractor responsibility. By managing the technical works, specialist trades and interfaces between them, we maintained a clear and unified approach from planning through to completion.
Arngask Primary School now has renewed building services and improved facilities to support pupils and staff in their everyday use of the school.